Cabinets: the long lead item that sets the finish schedule.

Cabinets are usually the last big order before drywall finishes and the first thing that holds up a unit turnover. From Asia, order to site runs 70 to 105 days. From Yucatán, about 37 days: a short sea crossing from Progreso, then 7 to 10 days by truck. The shorter the trip, the later you can lock the order and the less you carry in buffer stock.

Lead time by route

RouteOrder to siteWhat the time is spent on
Asia by ocean70 to 105 daysProduction, port, five to seven weeks of ocean and port time, inland delivery
Yucatán by sea, then truckAbout 37 daysFour to five weeks of production, a short Gulf crossing, 7 to 10 days by truck

What a shorter trip changes on a project

Orders can be placed after drawings settle, not months before. Shortages and damaged boxes are replaced in weeks, not another ocean cycle. Less inventory sits in a warehouse waiting for the building to be ready.

Lead times are Cabo Group figures for its own supply, to be replaced with dated shipment records from next quarter.